Initial Planning
- 20-02-2012 - Land deposit paid
- 22-11-2012 - Land settled
- 01-04-2013 - Initial Sales Quotation
- 30-04-2013 - Initial Deposit Paid
Contract
- 21-05-2013 - Soil Survey Test Conducted
- 23-05-2013 - Visit to Hopetun interiors and National tiles
- 18-06-2013 - First Tender
- 22-06-2013 - Second Tender
- 11-07-2013 - Tender finally signed
- 18-07-2013 - Hopetun and electrical
- 20-07-2013 - National Tiles
- 26-07-2013 - Contract Signed
Building
- 09-09-2013 - Site Start